Overview · Updated November 25, 2026

Data centers in Norway

The facilities being built and planned, with developer, size, status and known contractor. Everything comes from public sources, listed under each facility.

01

About this overview

This overview covers data centers in Norway that are under construction, recently put into operation or planned. It is built on public sources only: the developers' and contractors' own pages, the municipalities, the energy regulator NVE, the grid operator Statnett and edited media.

Industri Nord has not delivered to the facilities on this page. The overview is made for suppliers and others who want to know who is building, and how far the projects have come.

Size is given the way the source states it. Reserved grid capacity, total power and IT capacity are different measures and cannot be added together. The overview is not complete.

Report an error

02

Status in November 2026

On November 9, 2026, Statnett stated that data centers totaling 800 MW are connected to the grid, that 4,200 MW have reserved capacity, and that 9,100 MW are in the capacity queue. On top of that come requests for a further 18,000 MW. By comparison, peak power demand in Norway is just over 25,000 MW.

The same day, Statnett introduced a temporary halt to new grid capacity reservations for data centers. The halt is expected to be lifted by August 1, 2027, at the latest. Facilities that have had the required functional requirements approved can still be connected, and facilities already connected are not affected.

The business daily E24 has obtained the list of projects that had their technical applications in when the halt came, and that therefore proceed: Nscale in Narvik (115 MW), Google in Skien (120 MW), Green Mountain at Undheim (100 MW) and in Enebakk (75 MW), Bitzero in Namsskogan (70 MW), Lefdal Mine Datacenter (63 MW), Polar DC in Drangedal (55 MW) and Bulk in Kristiansand (25 MW). For 16 other projects that had reserved capacity, the future is less certain.

At the same time, the government announced that it aims to introduce a licensing scheme for data centers.

03

Fyresdal

At Molandsmoen in Fyresdal, Telemark, EdgeConneX is building a data center with six buildings.

Developer
EdgeConneX. The applicant in the building case is EdgeConneX MCN Norway AS.
Size
A grid connection of 365 MW. 140 MW is allocated, and 225 MW is waiting in the capacity queue. Six buildings with a footprint of about 6,000 square meters each, on three floors.
Status
Under construction since the first quarter of 2026. In November 2026, the steel structure of building 1 is being erected. Building 1 is scheduled for completion in 2027 and the last building in 2029.
Contractor
No main contractor is named on the project page. Suppliers can register in a form that the municipality and the developer link to. The municipality refers to it as CTS's form.

04

Narvik and Bjerkvik

The data center is next to the Skoglund industrial area in Kvandal, by Bjerkvik, in Narvik municipality in Nordland. The data center in Narvik, in Bjerkvik and at Kvandal is the same facility. It is also referred to as Stargate Norway.

Developer
Nscale. Operations will sit with Nordscale Operations AS, owned 51 percent by Nscale Norway AS and 49 percent by Nordkraft AS.
Size
230 MW of reserved grid capacity. Three buildings totaling 100 MW are under contract.
Status
Under construction. The three buildings are expected to be completed during 2027.
Contractor
HENT is building the three buildings (KNB4, KNB5 and KNB6) and is responsible for concrete, structure and architecture. CTS Nordics has a turnkey delivery that includes the technical installations.

05

Undheim

At Undheim in Time municipality, Rogaland, Green Mountain is building the SVG-Undheim data center for a single international customer.

Developer
Green Mountain. The license for the grid connection is held by Green Mountain Undheim Investment AS.
Size
80 MW of IT capacity and 100 MW of total power, in two interconnected buildings.
Status
Under construction. The facility is scheduled for completion in 2028. On November 6, 2026, NVE granted a license for the substation and a temporary grid connection.
Contractor
DC Nordic is the main contractor. DC Nordic is a joint venture between Backe and Bravida.

06

Skien

At Gromstul outside Skien, Telemark, Google is building a data center.

Developer
Google. The client in the contracts is WS Computing AS.
Size
240 MW allocated for the first phase. The first data center building is 28,000 square meters.
Status
Under construction. Google has stated that the facility will be operational in 2026.
Contractor
Skanska has the groundworks and the core and shell of the first data center, in a working partnership with its subsidiary Marthinsen & Duvholt. The shell contract covers the complete steel frame, exterior walls and roof.

07

Tydal

At Kirkvollen in Tydal, Trøndelag, an existing data center is being converted into a data center for artificial intelligence.

Developer
Tydal Data Center AS, a subsidiary of Bitdeer Technologies Group.
Size
180 MW of gross installed capacity. 121 MW of IT capacity is leased to Volta Tydal AS for 16 years.
Status
Under conversion. The first construction phase is planned to go into operation at the end of 2026 and the second in the first quarter of 2027.
Contractor
Data Center Installations AS (DCI), part of Sparc Group, is responsible for design and construction.

08

Hamar

At Heggvin in Hamar municipality, Innlandet, Green Mountain operates the OSL-Hamar data center, with TikTok as the only tenant.

Developer
Green Mountain.
Size
Three buildings totaling 90 MW. The plan is five buildings of 30 MW each, 150 MW in total.
Status
The first three buildings are complete and in operation. Two more buildings are planned.
Contractor
CTS Nordics was the main contractor for the first three buildings. No contractor is named for the next two.

09

Tonstad

At Ertsmyra by Tonstad in Sirdal municipality, Agder, GreenScale is planning the Tonstad DataPark data center.

Developer
GreenScale, through Tonstad Datapark AS.
Size
300 MW of secured grid capacity, according to the developer. Four data center buildings are planned on a site of 420,000 square meters.
Status
Planned. Site clearing started in February 2026, but on November 10, 2026, the County Governor of Agder annulled the municipality's change to the zoning plan, which had opened for a data center. GreenScale has said that it stands by the project and is assessing what the decision means.
Contractor
Not stated.

10

More facilities being built and expanded

Three more facilities are under construction or being expanded.

Porsgrunn
At Herøya, Polar DC is building the HER01 data center in the former REC premises, with around 40 MW in the first phase. The local daily Porsgrunns Dagblad names Jones Engineering as the main contractor.
Drangedal
In Tørdal, Polar DC has the DRA01 data center in operation with 12 MW of IT capacity, and the customer is Crusoe. The next phase, DRA02, is to add 40 MW of IT capacity and is expected to go live in late 2027.
Kristiansand and Vennesla
At Støleheia, Bulk Infrastructure is expanding its data center, which sits on the border between Vennesla and Kristiansand. The new substation will have a capacity of 900 MW, and 600 MW is reserved for Bulk.

11

Planned in southern and eastern Norway

These are places where a data center is planned but not under construction. No contractor is named in the sources, except where stated.

Bolvik in Skien
Grenland Data Center AS, owned by Løvenskiold-Fossum, has an option agreement with Skien Tomteselskap for a site at Bolvik. Nscale is to develop and operate the data center, and 576 MW has been applied for.
Gromstul in Skien
Aker Nscale and Løvenskiold-Fossum Kraft Drift have an agreement for a data center on the site next to Google's facility. The project has applied for 96 MW of grid capacity.
Kiseåsen in Skien
Cloudberry is planning a data center by the Rød substation. The planning program describes three units of about 40 MW of IT power each and around 160 MW of total electrical power, and a collaboration with CTS Nordics as the preferred EPC partner.
Bamble
At Frier Vest, BW Velora is planning a data center with a capacity of around 250 MW. A new zoning proposal for the area is to go out for public consultation.
Rjukan
Green Mountain has given notice that it is starting zoning work for a new data center in Rjukan Næringspark. The deadline for comments is December 15, 2026.
Flekkefjord
Reikna and Flekkefjord Handelseiendom want to establish a data center in the Trøngsla industrial area. The plans were due to be presented to the municipal executive board on November 12, 2026.
Sarpsborg
At Hasle, DC Sarpsborg is developing an area for a data center with a planned power need of 300 MW. The company is owned by Østfold Energi (66 percent) and Sarpsborg municipality (34 percent). The municipal executive board confirmed the planning program on September 24, 2026. No data center operator is in place, and the project has no reserved grid capacity.
Våler in Østfold
At Gylderåsen, Google holds the rights to develop a data center, and 480 MW is reserved in the grid. Construction is planned to start in 2030, and Google has not decided.

The three projects in Skien have no reserved grid capacity and must wait until the fall of 2027, according to the local daily Telemarksavisa.

12

Planned in western, central and northern Norway

Planned data centers in western Norway, Trøndelag and northern Norway, from south to north.

Sandnes
Microsoft has bought a site at Kvål and is planning a 25 MW data center. No construction schedule has been made public.
Mongstad
Arcem is planning two data centers: one in Alver municipality of up to 50 MW and one at Leirvåg in Austrheim of up to 75 MW. Both are in Statnett's capacity queue, and the next step is zoning.
Gulen
BW Velora wants to establish a data center in Skipavika Næringspark. The zoning change was out for consultation until October 27, 2026.
Ålesund
Tafjord planned a data center with a power need of up to 400 MW at Sjøholt. The planning committee in Ålesund municipality voted no to the plans on November 17, 2026.
Orkland
In Eiktyr Industripark, a subsidiary of Norsk Industriutvikling is planning a data center with a first phase of around 50 MW and possible expansion toward 450 MW. The ministry approved the area zoning plan on November 2, 2026, and specified that a data center must be zoned in a separate detailed plan.
Namsskogan
In Tunnsjødal, Bitzero is planning two to four data center buildings with a combined capacity of up to 110 MW. They are to replace today's 40 MW container-based solution. Skanska has the project development, and the aim is a separate contract for the construction.
Mo i Rana
T1 Energy wants to convert part of the Giga Arctic factory building into a data center. The municipality rezoned that part on August 27, 2026, and the company expects that a 50 MW data center could be operational in 2027.
Helgeland and Ballangsleira
Nscale has applied for 1 gigawatt for a data center in Helgeland and 140 MW for a data center at Ballangsleira in Narvik municipality.
Balsfjord
Nscale has proposed a data center at Stormoen. On September 28, 2026, the municipal council voted to continue studying the proposal.

13

What we build for data centers

We build the steel that carries power and cooling equipment, to your drawings, in Norway.

Pump and CDU skids
Frames for coolant distribution units, pumps, heat exchangers and manifolds, with leveling and drip containment.
Power and electrical skids
Steel bases that carry a transformer, switchgear or UPS block as one liftable unit.
Pipe racks and pipe supports
Repeatable racks, supports and bracing for piping and cable routes.
Equipment platforms and gantries
Roof and yard steel for chillers and dry coolers, with grating, handrail and access.
Steel enclosures and modules
Enclosed steel modules built to your dimensions when an open skid is not enough.

Proposed range. The scope is confirmed in the quote.

How we work

14 — FAQ

Questions

Who is building the data center in Fyresdal?

EdgeConneX is building the data center at Molandsmoen in Fyresdal. Construction started in the first quarter of 2026, and the first of six buildings is scheduled for completion in 2027.

Who is the contractor on the data center in Narvik?

HENT is building three buildings for Nscale at Kvandal by Bjerkvik and is responsible for concrete, structure and architecture. CTS Nordics has a turnkey delivery that includes the technical installations.

Are the data center in Bjerkvik and the data center in Narvik the same?

Yes. The facility is next to the Skoglund industrial area in Kvandal, by Bjerkvik, in Narvik municipality.

Who is building the data center at Undheim?

Green Mountain is the developer, and DC Nordic is the main contractor. DC Nordic is a joint venture between Backe and Bravida. The facility is scheduled for completion in 2028.

Who is building Google's data center in Skien?

Skanska has the groundworks and the core and shell of the first data center at Gromstul, in a working partnership with its subsidiary Marthinsen & Duvholt.

Can new data centers get grid capacity now?

On November 9, 2026, Statnett introduced a temporary halt to new grid capacity reservations for data centers. The halt is expected to be lifted by August 1, 2027, at the latest. Facilities that have had the functional requirements approved can still be connected.