About this overview
This overview covers data centers in Norway that are under construction, recently put into operation or planned. It is built on public sources only: the developers' and contractors' own pages, the municipalities, the energy regulator NVE, the grid operator Statnett and edited media.
Industri Nord has not delivered to the facilities on this page. The overview is made for suppliers and others who want to know who is building, and how far the projects have come.
Size is given the way the source states it. Reserved grid capacity, total power and IT capacity are different measures and cannot be added together. The overview is not complete.
Report an error02
Status in November 2026
On November 9, 2026, Statnett stated that data centers totaling 800 MW are connected to the grid, that 4,200 MW have reserved capacity, and that 9,100 MW are in the capacity queue. On top of that come requests for a further 18,000 MW. By comparison, peak power demand in Norway is just over 25,000 MW.
The same day, Statnett introduced a temporary halt to new grid capacity reservations for data centers. The halt is expected to be lifted by August 1, 2027, at the latest. Facilities that have had the required functional requirements approved can still be connected, and facilities already connected are not affected.
The business daily E24 has obtained the list of projects that had their technical applications in when the halt came, and that therefore proceed: Nscale in Narvik (115 MW), Google in Skien (120 MW), Green Mountain at Undheim (100 MW) and in Enebakk (75 MW), Bitzero in Namsskogan (70 MW), Lefdal Mine Datacenter (63 MW), Polar DC in Drangedal (55 MW) and Bulk in Kristiansand (25 MW). For 16 other projects that had reserved capacity, the future is less certain.
At the same time, the government announced that it aims to introduce a licensing scheme for data centers.
03
Fyresdal
At Molandsmoen in Fyresdal, Telemark, EdgeConneX is building a data center with six buildings.
- Developer
- EdgeConneX. The applicant in the building case is EdgeConneX MCN Norway AS.
- Size
- A grid connection of 365 MW. 140 MW is allocated, and 225 MW is waiting in the capacity queue. Six buildings with a footprint of about 6,000 square meters each, on three floors.
- Status
- Under construction since the first quarter of 2026. In November 2026, the steel structure of building 1 is being erected. Building 1 is scheduled for completion in 2027 and the last building in 2029.
- Contractor
- No main contractor is named on the project page. Suppliers can register in a form that the municipality and the developer link to. The municipality refers to it as CTS's form.
04
Narvik and Bjerkvik
The data center is next to the Skoglund industrial area in Kvandal, by Bjerkvik, in Narvik municipality in Nordland. The data center in Narvik, in Bjerkvik and at Kvandal is the same facility. It is also referred to as Stargate Norway.
- Developer
- Nscale. Operations will sit with Nordscale Operations AS, owned 51 percent by Nscale Norway AS and 49 percent by Nordkraft AS.
- Size
- 230 MW of reserved grid capacity. Three buildings totaling 100 MW are under contract.
- Status
- Under construction. The three buildings are expected to be completed during 2027.
- Contractor
- HENT is building the three buildings (KNB4, KNB5 and KNB6) and is responsible for concrete, structure and architecture. CTS Nordics has a turnkey delivery that includes the technical installations.
Sources
- HENT: contract to build Nscale's data center, September 2, 2026 (in Norwegian)
- CTS Group: expanded partnership with Nscale at Kvandal, September 4, 2026
- NVE: license for the new Skoglund substation, March 11, 2026 (in Norwegian)
- Nscale: Nordscale Operations AS, July 6, 2026
- Narvik municipality: Narvik to host Europe's first OpenAI data center, July 31, 2025 (in Norwegian)
05
Undheim
At Undheim in Time municipality, Rogaland, Green Mountain is building the SVG-Undheim data center for a single international customer.
- Developer
- Green Mountain. The license for the grid connection is held by Green Mountain Undheim Investment AS.
- Size
- 80 MW of IT capacity and 100 MW of total power, in two interconnected buildings.
- Status
- Under construction. The facility is scheduled for completion in 2028. On November 6, 2026, NVE granted a license for the substation and a temporary grid connection.
- Contractor
- DC Nordic is the main contractor. DC Nordic is a joint venture between Backe and Bravida.
06
Skien
At Gromstul outside Skien, Telemark, Google is building a data center.
- Developer
- Google. The client in the contracts is WS Computing AS.
- Size
- 240 MW allocated for the first phase. The first data center building is 28,000 square meters.
- Status
- Under construction. Google has stated that the facility will be operational in 2026.
- Contractor
- Skanska has the groundworks and the core and shell of the first data center, in a working partnership with its subsidiary Marthinsen & Duvholt. The shell contract covers the complete steel frame, exterior walls and roof.
Sources
- Google Norway: construction start in Skien, February 7, 2024 (in Norwegian)
- Skanska Norway: Skanska to build the core and shell of the data center, November 15, 2024 (in Norwegian)
- Skanska: the Datasenter Skien project page (in Norwegian)
- NRK: new rules for data centers, November 9, 2026 (in Norwegian)
07
Tydal
At Kirkvollen in Tydal, Trøndelag, an existing data center is being converted into a data center for artificial intelligence.
- Developer
- Tydal Data Center AS, a subsidiary of Bitdeer Technologies Group.
- Size
- 180 MW of gross installed capacity. 121 MW of IT capacity is leased to Volta Tydal AS for 16 years.
- Status
- Under conversion. The first construction phase is planned to go into operation at the end of 2026 and the second in the first quarter of 2027.
- Contractor
- Data Center Installations AS (DCI), part of Sparc Group, is responsible for design and construction.
08
Hamar
At Heggvin in Hamar municipality, Innlandet, Green Mountain operates the OSL-Hamar data center, with TikTok as the only tenant.
- Developer
- Green Mountain.
- Size
- Three buildings totaling 90 MW. The plan is five buildings of 30 MW each, 150 MW in total.
- Status
- The first three buildings are complete and in operation. Two more buildings are planned.
- Contractor
- CTS Nordics was the main contractor for the first three buildings. No contractor is named for the next two.
09
Tonstad
At Ertsmyra by Tonstad in Sirdal municipality, Agder, GreenScale is planning the Tonstad DataPark data center.
- Developer
- GreenScale, through Tonstad Datapark AS.
- Size
- 300 MW of secured grid capacity, according to the developer. Four data center buildings are planned on a site of 420,000 square meters.
- Status
- Planned. Site clearing started in February 2026, but on November 10, 2026, the County Governor of Agder annulled the municipality's change to the zoning plan, which had opened for a data center. GreenScale has said that it stands by the project and is assessing what the decision means.
- Contractor
- Not stated.
10
More facilities being built and expanded
Three more facilities are under construction or being expanded.
- Porsgrunn
- At Herøya, Polar DC is building the HER01 data center in the former REC premises, with around 40 MW in the first phase. The local daily Porsgrunns Dagblad names Jones Engineering as the main contractor.
- Drangedal
- In Tørdal, Polar DC has the DRA01 data center in operation with 12 MW of IT capacity, and the customer is Crusoe. The next phase, DRA02, is to add 40 MW of IT capacity and is expected to go live in late 2027.
- Kristiansand and Vennesla
- At Støleheia, Bulk Infrastructure is expanding its data center, which sits on the border between Vennesla and Kristiansand. The new substation will have a capacity of 900 MW, and 600 MW is reserved for Bulk.
11
Planned in southern and eastern Norway
These are places where a data center is planned but not under construction. No contractor is named in the sources, except where stated.
- Bolvik in Skien
- Grenland Data Center AS, owned by Løvenskiold-Fossum, has an option agreement with Skien Tomteselskap for a site at Bolvik. Nscale is to develop and operate the data center, and 576 MW has been applied for.
- Gromstul in Skien
- Aker Nscale and Løvenskiold-Fossum Kraft Drift have an agreement for a data center on the site next to Google's facility. The project has applied for 96 MW of grid capacity.
- Kiseåsen in Skien
- Cloudberry is planning a data center by the Rød substation. The planning program describes three units of about 40 MW of IT power each and around 160 MW of total electrical power, and a collaboration with CTS Nordics as the preferred EPC partner.
- Bamble
- At Frier Vest, BW Velora is planning a data center with a capacity of around 250 MW. A new zoning proposal for the area is to go out for public consultation.
- Rjukan
- Green Mountain has given notice that it is starting zoning work for a new data center in Rjukan Næringspark. The deadline for comments is December 15, 2026.
- Flekkefjord
- Reikna and Flekkefjord Handelseiendom want to establish a data center in the Trøngsla industrial area. The plans were due to be presented to the municipal executive board on November 12, 2026.
- Sarpsborg
- At Hasle, DC Sarpsborg is developing an area for a data center with a planned power need of 300 MW. The company is owned by Østfold Energi (66 percent) and Sarpsborg municipality (34 percent). The municipal executive board confirmed the planning program on September 24, 2026. No data center operator is in place, and the project has no reserved grid capacity.
- Våler in Østfold
- At Gylderåsen, Google holds the rights to develop a data center, and 480 MW is reserved in the grid. Construction is planned to start in 2030, and Google has not decided.
The three projects in Skien have no reserved grid capacity and must wait until the fall of 2027, according to the local daily Telemarksavisa.
Sources
- E24: Bolvik and the site next to Google at Gromstul, September 16, 2026 (in Norwegian)
- Telemarksavisa: the planned data centers in Skien, November 25, 2026 (in Norwegian)
- NRK: plans to build a data center in Skien, January 29, 2026 (in Norwegian)
- Skien municipality: planning program for Kiseåsen, August 21, 2026 (in Norwegian)
- Frier Vest and BW Velora: agreement on a data center, May 29, 2026 (in Norwegian)
- Porsgrunns Dagblad: a new turn for the data center at Frier, November 19, 2026 (in Norwegian)
- Tinn municipality: notice of zoning work in Rjukan Næringspark, November 11, 2026 (in Norwegian)
- NRK: plans for a data center in Flekkefjord, November 12, 2026 (in Norwegian)
- DC Sarpsborg: the Hasle project page (in Norwegian)
- Østfold Energi: the projects at Hasle and Gylderåsen (in Norwegian)
- Sarpsborg municipality: decisions of the executive board, September 24, 2026 (in Norwegian)
- Sarpsborg Arbeiderblad: Statnett's halt and Hasle, November 9, 2026 (in Norwegian)
- Montel: 480 MW reserved for a data center in Østfold, September 15, 2026 (in Norwegian)
- NRK: planned data centers in Østfold, October 1, 2026 (in Norwegian)
12
Planned in western, central and northern Norway
Planned data centers in western Norway, Trøndelag and northern Norway, from south to north.
- Sandnes
- Microsoft has bought a site at Kvål and is planning a 25 MW data center. No construction schedule has been made public.
- Mongstad
- Arcem is planning two data centers: one in Alver municipality of up to 50 MW and one at Leirvåg in Austrheim of up to 75 MW. Both are in Statnett's capacity queue, and the next step is zoning.
- Gulen
- BW Velora wants to establish a data center in Skipavika Næringspark. The zoning change was out for consultation until October 27, 2026.
- Ålesund
- Tafjord planned a data center with a power need of up to 400 MW at Sjøholt. The planning committee in Ålesund municipality voted no to the plans on November 17, 2026.
- Orkland
- In Eiktyr Industripark, a subsidiary of Norsk Industriutvikling is planning a data center with a first phase of around 50 MW and possible expansion toward 450 MW. The ministry approved the area zoning plan on November 2, 2026, and specified that a data center must be zoned in a separate detailed plan.
- Namsskogan
- In Tunnsjødal, Bitzero is planning two to four data center buildings with a combined capacity of up to 110 MW. They are to replace today's 40 MW container-based solution. Skanska has the project development, and the aim is a separate contract for the construction.
- Mo i Rana
- T1 Energy wants to convert part of the Giga Arctic factory building into a data center. The municipality rezoned that part on August 27, 2026, and the company expects that a 50 MW data center could be operational in 2027.
- Helgeland and Ballangsleira
- Nscale has applied for 1 gigawatt for a data center in Helgeland and 140 MW for a data center at Ballangsleira in Narvik municipality.
- Balsfjord
- Nscale has proposed a data center at Stormoen. On September 28, 2026, the municipal council voted to continue studying the proposal.
Sources
- Microsoft: the data center in Sandnes, June 30, 2026 (in Norwegian)
- Digi: Microsoft to build a data center in Sandnes, June 30, 2026 (in Norwegian)
- Arcem: two data centers at Mongstad, October 20, 2026 (in Norwegian)
- Gulen municipality: consultation on the zoning change in Skipavika Næringspark, September 28, 2026 (in Norwegian)
- NRK: no to the data center at Sjøholt, November 17, 2026 (in Norwegian)
- Norsk Industriutvikling: the data center in Eiktyr Industripark, May 31, 2026 (in Norwegian)
- Norwegian government: decision on the area zoning plan for Eiktyr Industripark, November 2, 2026 (in Norwegian)
- Skanska: Skanska to develop a data center in Namsskogan with Bitzero, October 20, 2026 (in Norwegian)
- T1 Energy: Giga Arctic approved for data center development, August 27, 2026
- Digi: Nscale's applications in Helgeland and at Ballangsleira, September 2, 2026 (in Norwegian)
- NRK: data center in Balsfjord, September 28, 2026 (in Norwegian)
13
What we build for data centers
We build the steel that carries power and cooling equipment, to your drawings, in Norway.
- Pump and CDU skids
- Frames for coolant distribution units, pumps, heat exchangers and manifolds, with leveling and drip containment.
- Power and electrical skids
- Steel bases that carry a transformer, switchgear or UPS block as one liftable unit.
- Pipe racks and pipe supports
- Repeatable racks, supports and bracing for piping and cable routes.
- Equipment platforms and gantries
- Roof and yard steel for chillers and dry coolers, with grating, handrail and access.
- Steel enclosures and modules
- Enclosed steel modules built to your dimensions when an open skid is not enough.