Skid-based modular data centers

What a skid is, how it differs from a container and a module, how it is moved and set, and what to settle before fabrication starts.

01

What a skid-based data center is

A skid is a welded steel base frame. Power or cooling equipment is mounted on it in a shop, and the whole assembly is shipped, lifted and bolted down as one unit.

A skid-based data center is a facility put together from such units inside a building or a shell. Each skid carries one part of the plant. Capacity is added by setting another skid, not by building another room.

The frame does three jobs. It carries the equipment on the road and in the lift. It gives the points where the unit is anchored. And it stays as the permanent base once the unit is running.

02

Skid, container or module

The three formats differ in the enclosure. That decides where the unit can stand and what has to carry wind, snow and rain.

SkidContainerPrefabricated module
EnclosureOpen steel frameClosed ISO containerCustom steel enclosure
Where it sitsInside a building or under a canopyOutdoors on a pad, or inside a shell buildingOutdoors on a foundation
Weather loadsCarried by the host buildingCarried by the container shellCarried by the module structure
TransportFlatbed. Fork pockets or lifting lugsContainer chassis. Corner castingsOften oversize. Planned route and crane
Best forPower and cooling blocks inside a hallA complete unit on a new padSizes a container cannot give

A skid has no walls or roof, so the building around it takes the weather. A container or a module stands on its own outdoors and must carry those loads itself. Cutting large openings in a container shell removes strength, so a modified container has to be checked again.

03

Common skid types

Skids are grouped by the system they carry. Each type loads the frame in a different way.

Power skids
Switchgear, transformers and UPS on one frame. A transformer puts most of the weight at one end, so the center of gravity must be marked for the lift.
Cooling skids
Pumps, heat exchangers and coolant distribution units. Rotating equipment gives vibration, and the weight changes between empty and filled.
Energy storage skids
Battery cabinets. Batteries are dense, so floor load and anchor forces are high for the footprint.
IT skids
Rack rows mounted on a frame. Rows are tall and narrow, so tipping is the case to check.
What is a CDU?

04

Why prefabricate

The shop and the site work at the same time. The pad is poured while the skid is built, and the two meet on one day.

Work moves from a crowded site into a shop with cranes, fixtures and a test bench. Units built to the same drawings come out the same, and a finished unit can be stored or moved to another site.

The trade-off is the interface. The connection between the unit and its foundation becomes a design item of its own, with anchor layout, leveling and tolerances that both sides must agree on.

05

How a skid is moved, lifted and set

A skid leaves the shop on a flatbed, braced and tied down. Braking, cornering and rough roads load the frame with the equipment already mounted, so the frame is designed for the trip as well as for the place it ends up.

On site the unit is lifted through fork pockets or by crane through lifting lugs. A spreader bar keeps the slings close to vertical. The lift plan shows the center of gravity, the sling angles and the load on each lug. Lugs sized for the bare frame are a common problem once the equipment is on.

The unit is set on a pad, a thickened slab, piers or a steel platform. The surface must be level within what the equipment maker requires. Then the unit is anchored and connected.

06

Who owns the interface

The most common gap on modular projects is an interface nobody owns. The fabricator assumes the site engineer designs the anchors. The site engineer assumes they are in the fabricator's drawings. The skid arrives with a hole pattern that does not match the pad.

The structural design follows the rules of the country where the unit is installed. Whatever the rules, the same four things must be given to named parties before fabrication starts.

The frame
Who designs it, for which load cases: installed, transport and lifting.
The reactions
Who gives the forces at each anchor point to the site engineer.
The pad and the anchors
Who designs the foundation and the anchor layout, including for units added later.
The inspection
Who checks the unit in the shop and the anchoring on site.
How to specify steel for a data center

07

What to send a fabricator

A fabricator can price from drawings. Without drawings, these six things are enough to start.

Equipment and loads
Manufacturer drawings and weights for everything mounted on the frame.
Interfaces
Bolt patterns, pipe and cable entry points, anchor layout.
Lifting and transport
How the unit will be lifted and any limits on size for the road.
Environment and finish
Indoor or outdoor, and the surface treatment you require.
Scope
Steel only, or with mounting, piping, wiring and testing.
Quantity and dates
Number of units and when they must be on site.

08 — Why

Why build on a skid

  1. 01

    The pad is poured while the skid is built. The two meet on one day.

  2. 02

    Work moves from a crowded site into a shop with cranes and a test bench.

  3. 03

    Every unit is built to the same drawings, so the next one fits like the first.

  4. 04

    A finished skid can be stored, moved and reused at another site.

09 — FAQ

Questions

What is a skid in a data center?

A welded steel base frame that carries electrical or mechanical equipment, so the whole assembly can be shipped, lifted and bolted down as one unit.

What is a CDU skid?

The frame that carries a coolant distribution unit with its pumps, heat exchanger and manifolds for liquid-cooled racks.

What is the difference between a skid, a container and a prefabricated module?

A skid is an open frame that sits inside a building or under a canopy. A container is a closed ISO box. A prefabricated module is a closed enclosure built to custom dimensions.