Factory acceptance test (FAT)

What a factory acceptance test is, what is checked on a skid before it leaves the shop, what to agree in advance, and how it differs from the test on site.

01

What a FAT is

A factory acceptance test, FAT, is a test of a finished unit at the place where it was built, before it is shipped. It shows that the unit is in accordance with the specification.

The term is defined in IEC 62381, the standard for acceptance tests of automation systems in the process industry: an activity, including inspection and testing, that demonstrates that the system is in accordance with the specification, typically carried out at the vendor's facility. The same word is used for packaged equipment such as skids. There the content of the test is set by the order.

The reason to test in the shop is simple. A fault found there is fixed with the tools, the people and the crane at hand. The same fault found on site waits for parts and holds up the trades around it.

02

FAT, SAT and SIT

Three tests carry similar names. They differ in where they are done and what they show.

FAT, factory acceptance test
At the vendor's facility, before shipping. Shows that the unit meets the specification.
SAT, site acceptance test
On site, after the unit is set and connected. Shows that it still meets the specification after transport and installation.
SIT, site integration test
On site. Shows that the unit works together with the systems around it.

Loop checks and commissioning are separate activities and come in addition to these tests.

03

What is checked on a skid

What is tested follows from what was built in the shop. A bare frame is measured and inspected. A unit with pumps, pipework and controls is also tested as a system.

The steel
Dimensions against the drawing, the flatness of the equipment supports, the welds, the surface treatment, and the position of lifting points and anchor holes.
The equipment
That each item is the one ordered, that it is aligned, and that the bolts are tightened as specified.
The pipework
A pressure or leak test, cleanliness, and the position of each connection flange.
The wiring
Earthing, insulation and continuity, and that each signal reaches the right terminal.
The function
That pumps, valves and controls do what the specification says, as far as it can be shown without the rest of the plant.

Steel is the confirmed scope. The other levels are agreed in the quote.

See the four levels

04

What to agree before the test

A test without an agreed procedure ends in a discussion. These six points are worth settling when the order is placed, not on the day.

The procedure
A written test procedure, with each step and its acceptance criterion.
Who attends
Who witnesses the test for the buyer, and how much notice the workshop gives.
What the shop provides
Water, power, test medium and instruments, and what is simulated because the rest of the plant is not there.
The punch list
How findings are recorded, who closes them, and which ones must be closed before shipping.
The record
A signed report with the results, the instruments used and the open points.
What it releases
Whether a passed test releases shipping, a payment, or both.

05

The documents that follow the unit

The test report is one part of the documentation. For the steel, the package also holds the inspection documents for the material, the welding records and the report on the surface treatment. Which documents you get is set by the order.

How to specify steel for a data center

06

After the FAT

A passed FAT does not replace the test on site. Transport and installation can move what was aligned in the shop, and the connections to the rest of the plant are first made on site.

Keep the results from the shop, so the test on site can be compared with them.

07 — FAQ

Questions

What does FAT stand for?

Factory acceptance test. It is a test of a finished unit at the place where it was built, before it is shipped, to show that the unit is in accordance with the specification.

What is the difference between FAT and SAT?

The place and the time. A FAT is done at the vendor's facility before shipping. A SAT, site acceptance test, is done on site after the unit is installed. The FAT finds faults while they are easy to fix. The SAT shows that the unit still works after transport and installation.

Who attends a FAT?

The vendor runs the test, and the buyer or someone acting for the buyer witnesses it. Who attends, and how much notice they get, should be agreed when the order is placed.

Is a FAT always done?

No. A FAT is agreed in the order, together with what it covers. If the unit leaves the shop with equipment, pipework or controls on it, a FAT is the usual way to show that it works before it ships.

Does a bare steel frame get a FAT?

A bare frame has no function to test. It is measured and inspected: dimensions, welds, surface treatment, and the position of lifting points and anchor holes. The buyer can inspect it before it ships.