Guide · Updated November 25, 2026

How to specify steel for a data center

The points to settle and write into the order before fabrication starts: execution class, weld quality, documents, surface treatment, loads, model and delivery.

01

What a specification settles

A steel frame is built to a drawing, and the drawing does not say everything. How strictly the steel is welded and tested, which documents follow it, and how it is protected, are set by the order. Where the order is silent, each supplier fills the gap in its own way, and the quotes cannot be compared.

This guide takes the points one at a time: what each one means, who decides it, and what to ask for. Most of the standards named here are European standards, which Norway, Sweden, Denmark and Finland all adopt as national standards.

02

EN 1090 and the execution class

EN 1090 is the European standard for the execution of steel structures. Part 1 describes how a fabricator documents load-bearing components and CE-marks them. Part 2 gives the technical requirements for the work itself.

Part 2 has four execution classes, EXC1 to EXC4. EXC1 is the lowest and EXC4 the strictest. The class sets how the steel is welded, how much of it is tested, and how far each part can be traced.

The class is chosen by the structural designer, from the type of structure, the loads and the consequences of a failure. It can be set for a whole structure, for a part of it or for a single detail. The workshop does not choose it. Write the class into the order.

A higher class than the structure needs adds cost and no safety. If one requirement from a higher class is wanted, such as full traceability, it can be added to the order on its own.

The certificate
Ask for the fabricator's certificate for factory production control under EN 1090-1. It is issued by a notified body, and it states the execution class the workshop is certified for.
The class
A workshop certified for EXC3 can build EXC1, EXC2 and EXC3. A workshop certified for EXC2 can build EXC1 and EXC2.
The date and the body
Check that the certificate is valid for the period of the contract, and that the number of the notified body is in the EU database of notified bodies.
The declaration
Steel that EN 1090-1 covers is delivered with CE marking and a declaration of performance.

Not every frame is covered by Part 1. It applies to load-bearing components in construction works, and stairs and walkways that are an integral part of a machine are on the list of items it does not cover. The designer settles which rules apply to a frame. The technical requirements in Part 2 can be agreed in the order either way.

03

Weld quality and ISO 3834

ISO 3834 sets quality requirements for fusion welding. EN 1090-2 decides which part of it applies, by execution class.

EXC1
ISO 3834-4, elementary quality requirements.
EXC2
ISO 3834-3, standard quality requirements.
EXC3 and EXC4
ISO 3834-2, comprehensive quality requirements.

Welders are qualified to EN ISO 9606-1. From EXC2 the welding is led by welding coordination personnel as described in EN ISO 14731.

All welds are inspected visually along their full length. A share of them is also tested with other methods, such as magnetic particle or ultrasonic testing. How large the share is depends on the type of joint and the execution class.

Ask for the welding certificate that follows the certificate under EN 1090-1, and check that it covers the steel grades in the order.

04

Material certificates and traceability

Steel is delivered with an inspection document under EN 10204. The standard has four types, and the order should say which one is required.

Type 2.1
Declaration of compliance with the order. The manufacturer states that the products comply, without test results.
Type 2.2
Test report. The manufacturer states compliance and gives test results from non-specific inspection.
Type 3.1
Inspection certificate with test results from specific inspection, validated by the manufacturer's inspection representative, who is independent of the manufacturing department.
Type 3.2
As 3.1, but prepared together with the purchaser's inspector or an inspector designated by official regulations.

Traceability means that each part of the finished frame can be linked to the steel it was cut from, and to the document for that steel. EXC2 asks for partial traceability and EXC3 for full traceability. Full traceability can also be ordered for a frame in EXC2.

Ask for the documents as one package with the delivery: the inspection documents for the steel, the welding records, the test reports and the declaration of performance.

05

Surface treatment and corrosivity category

How long the steel lasts depends on where it stands. ISO 12944-2 sorts the atmosphere around a steel structure into six corrosivity categories.

C1, very low
Heated buildings with clean air, such as offices.
C2, low
Unheated buildings where condensation can occur, and rural areas with little pollution.
C3, medium
Urban and industrial air with moderate pollution, and coasts with low salinity.
C4, high
Industrial areas, and coasts with moderate salinity.
C5, very high
Coasts with high salinity, and places with almost permanent condensation and high pollution.
CX, extreme
Offshore areas with high salinity, and industry with extreme humidity and an aggressive atmosphere.

The category is set for the place where each frame stands. A frame in a heated hall and a frame on a roof at the coast are in different categories, even on the same site.

For a paint system, state the category and the durability. ISO 12944-1 has four durability ranges: low, up to 7 years; medium, 7 to 15 years; high, 15 to 25 years; and very high, more than 25 years. The range is the expected time to the first major maintenance painting. It is not a guarantee period.

Steel that stands outdoors is often hot-dip galvanized instead of painted, to EN ISO 1461.

06

Loads: snow, wind and the equipment

A frame is designed for the loads at the place where it stands. In Norway the building regulations, TEK17, say that the requirements for structural safety can be met by designing to the Eurocodes, NS-EN 1990 and NS-EN 1991 to NS-EN 1999, with the Norwegian national annexes. Snow loads are in Eurocode 1 part 1-3, and wind actions in part 1-4.

The structural designer sets the loads. What the supplier needs from you is the location of the site, whether the frame stands indoors or outdoors, and the weight of the equipment, dry and filled.

Building data centers in the Nordics

07

Drawings and the model

The workshop builds from the drawings it is given. Say which revision is the one to build from, and who approves a change.

If the project has a 3D model, agree on the file format the frame is exchanged in, and on who checks it against pipes, cable routes and the building before the steel is cut. A clash found in the model is moved on the screen. The same clash found on site is cut and welded.

If you only have a layout, say so. Then the frame has to be designed before it can be built, and your engineer should check that design before fabrication starts.

08

EPD and the footprint of the steel

An environmental product declaration, EPD, is a short document that sums up the environmental profile of a product in a standardized way. It is built on a life cycle assessment, follows ISO 14025 and is verified by an independent third party.

An EPD belongs to a product from a producer. If the project counts emissions, ask for the EPD of the steel that will be used in the frame, and write the requirement into the order before the steel is bought.

09

Lifting, transport and test

State how the unit will be lifted, and what the road allows. Ask for lifting points designed for the weight with the equipment mounted, and for the center of gravity to be marked on the unit.

If the unit leaves the shop with equipment, pipework or wiring on it, agree on what is tested before it ships, who attends, and what is written down.

Factory acceptance test (FAT)

10

What to send with the request

Drawings answer most of this. Without drawings, these six points are enough to start.

Equipment and loads
Manufacturer drawings and weights for everything mounted on the frame.
Interfaces
Bolt patterns, pipe and cable entry points, anchor layout.
Lifting and transport
How the unit will be lifted and any limits on size for the road.
Environment and finish
Indoor or outdoor, and the surface treatment you require.
Scope
Steel only, or with mounting, piping, wiring and testing.
Quantity and dates
Number of units and when they must be on site.
How we work

11 — FAQ

Questions

Who decides the execution class?

The structural designer. The class is chosen from the type of structure, the loads and the consequences of a failure, and it can differ between parts of the same structure. The workshop does not choose the class, but it must be certified for the class the order states.

Is EXC3 better than EXC2?

It is stricter, not better. EXC3 means more testing, full traceability and comprehensive quality requirements for welding. For steel that does not need it, that is cost without added safety. A single requirement from a higher class can be added to the order on its own.

What is the difference between EN 1090-1 and EN 1090-2?

Part 1 is about documentation, and Part 2 is about the work. Part 1 describes how a fabricator documents load-bearing components and CE-marks them. Part 2 gives the technical requirements for the steelwork, with the four execution classes.

What is a 3.1 certificate?

An inspection certificate under EN 10204. The manufacturer declares that the delivered products comply with the order and gives test results from specific inspection. The certificate is validated by the manufacturer's inspection representative, who is independent of the manufacturing department.

Which corrosivity category is a data center in?

It depends on where each frame stands, not on the type of building. ISO 12944-2 sorts environments from C1, heated buildings with clean air, to CX, offshore. Steel on a roof or in a yard near the coast is in a higher category than steel in a heated hall.

Does a skid need CE marking under EN 1090-1?